Levy of Liquidated Damages by Government Authority cannot be Arbitrary

Levy of Liquidated Damages by Government Authority cannot be Arbitrary

The litigation team of Singhania & Partners LLP (Bangalore) comprising of Ms. Shilpa Shah (Senior Partner) & Ms. Madhu Murthy G.K (Senior Associate) have successfully obtained two favourable awards in favour of their client Punj Lloyd- Sembawang – Sembawang India-Joint venture before the Arbitral Tribunal comprising of three members with presiding arbitrator being the retried High court Judge. The contracts were awarded  by  Bangalore Metro Rail Corporation Limited to consortium of Punj Lloyd Limited, Sembawang Engineers and Constructions Pte Ltd -Singapore & Sembawang Infrastructure (India) Pvt. Ltd. for construction of  (i) three Elevated Metro Stations i.e., Mysore Road Terminal, Deepanjalinagar and Magadi Road in Reach – 2 for Bangalore Metro rail Project, Phase -1 wherein, the executed Contract value was INR 150 Crores (USD 21.17 Million) and (ii) three Elevated Metro Stations i.e., Rajajinagar, Kuvempu Road and Malleshwaram in Reach – 3 for Bangalore Metro rail Project, Phase -1 wherein, the executed Contract value was INR 120 Crores (USD 16.94 Million) (hereinafter referred to as the two Projects)

The Arbitral Tribunal by allowing majority of the claims has held that Punj Lloyd -Sembawang Singapore- Sembawang India – Joint Venture (hereinafter referred to as the Contractor) is not liable to pay any liquidated damages/ Penalties levied by Bangalore Metro Rail Corporation Limited (hereinafter referred to as Bangalore Metro) by declaring the communications issued by Bangalore Metro for deposit of Liquidated Damages towards delay in completion of the two Projects as illegal and invalid. The exhaustive and meticulous Arbitral Awards in respect of the aforesaid disputes is in itself in the form of a mini thesis on a typical Indian Civil Engineering (Construction) Dispute resolved through Alternative Dispute Resolution by way of invoking the Arbitration clause in the Contract. In this update, we have attempted to focus only on ‘Contractor’s Liability towards Liquidated Damages’ in the event of delay in completion of Projects which is of such a high magnitude in complex Construction Contracts.

INTRODUCTION

 The Arbitral Tribunal in the aforesaid disputes had the opportunity to examine various provisions of the Indian Contract Act, Arbitration and Conciliation Act, 1996 as amended by the Amendment Act of 2015, Limitation Act and numerous judgments of different High Courts as well as conflicting decisions of the Apex Court in order to determine the claims of the Contractor and counter claims of Bangalore Metro. The Tribunal has accepted majority of the arguments raised by the Counsel for the Contractor by giving a specific finding with respect to the withholding of amounts in Interim Payment Certificates that a Public Authority like Bangalore Metro cannot resort to unjustified and baseless withholding of amounts due to the Contractor and awarded the same with interest.

FACTS OF THE CASE

The Contractor entered into Contracts with Bangalore Metro for the purpose of construction of elevated Metro Stations in respect of the two Projects. The duration of the Projects was twenty-two months commencing from 13th April 2009 to 13th February 2011 in case of the first Project which stretched upto 31st August 2015. In case of the second Project, twenty-two months commenced on 25th March 2009 and concluded on 24th January 2011, but the work stretched upto 30th June 2014 due to delays caused on account of various reasons. Consequently, the Contractor sought for extension of time as provided under the Contract on five occasions for completion of the works. Bangalore Metro had given four extensions without levy of any penalties or liquidated damages (LD) but while granting the 5th EOT, Bangalore Metro gave a post facto approval with levy of LD of INR 32 Crores (UDS 4.6 Million) for the Projects. Bangalore Metro also withheld all the Bank Guarantees (BGs) furnished by the Contractor, Final Bills, amounts towards various works executed towards non-tendered items, etc.

The dispute arose from contract on various counts in addition to wrongful levying of LD. Main contentions raised on behalf of the Contractor with respect to levying of LD  were that while granting first four extensions, no penalty or LD were levied and having delayed the approval of the final extension, Bangalore Metro had given the Contractor the impression that even final extension would be granted without any LD based on which the Contractor completed the work. Hence, Bangalore Metro was not justified in levying LD with retrospective effect especially when the General Consultant (GC) of Bangalore Metro had recommended the final extension without imposition of LD; and that Bangalore Metro after the commencement of train operations for nearly 1 ½ years, could not have achieved any productivity by levying LD and the only reason for imposition of LD was to withhold the various amounts legally due under the Contracts to the Contractor.

The Contractor before invoking the arbitration clause for resolution of disputes had approached the High Court of Karnataka at Bengaluru wherein, it had successfully obtained an order of stay over the implementation of the communication levying LDs in both the Projects till the constitution of Arbitral Tribunal, as there was an imminent threat that Bangalore Metro would encash the BGs furnished by the Contractor in order to recover the LD. Once Arbitral Tribunal was constituted, the Contractor filed an application under Section 17 of the Arbitration & Conciliation Act, 1996 restraining Bangalore Metro from invoking the communication levying LDs in respect of both the Projects till the disposal of the arbitration proceedings which came to be allowed. Bangalore Metro was also restrained form invoking the BGs amounting to INR 26 Crores (USD 3.7 Million).

The Contractor raised several monetary claims before the Arbitral Tribunal including claims for idling and overstay on account of delay by Bangalore Metro & breach of Contractual terms, release of payment towards Final bill, Non-tendered items for which rate analysis was not approved either by GC or by Bangalore Metro, Quantity variation and Price variation after defreezing the price, which was frozen while granting extension, totalling to INR 92 Crores (USD 13.15 Million) and INR 57 Crores (USD 8.15 Million) exclusive of interest, in respect of the first and second Projects respectively. In addition to that, directions were sought for release of BGs, issuance of Performance Certificate and declaration that Contractor is not liable to pay any penalty/ LD. Bangalore Metro raised counter claims towards LD, penalty for not achieving Key dates, loss of productivity, extension of services of GC, recovery of land rental charges and risk & cost amounting INR 87 Crores (USD 12.5 Million) and INR 33.6 Crores (USD 4.10 Million) in respect of the first and second Projects respectively. Voluminous records were placed before the Tribunal by leading both oral and documentary evidence followed by rigorous arguments from both the parties, after which the matters were reserved for passing of Awards.

OUTCOME

 The issue raised before the Tribunal involved the rights and liabilities of the parties in respect of a Construction Contract related to Projects of vast public importance. The main issue in controversy between the parties was – who was attributable for delayed progress of the Projects. The Contractor had meticulously established before the Tribunal that delay in  handing over of lands & Good for Construction Drawings, entrustment of additional works, delay in granting of approvals by Bangalore Metro, delay in supply of materials by Vendors on account of belated release of payments towards Interim Bills, Force Majeure, freezing of indices, etc., had contributed to the delay in progress of works on account of which Contractor could not achieve the Key Dates. We were successful in establishing various claims of the Contractor and demolishing Bangalore Metro’s counter claims in its entirety amounting to about 17 Millions USD.

In the light of the evidence and submissions placed before the Tribunal, it was held that the Contractor had successfully executed the Projects and there was no reasons forthcoming for imposition of LD after the completion of the entire Project and commencement of commercial operations. The Tribunal specifically relied upon the fact that having allowed the Contractor to complete the works without approval of the final extension and levying of LD with retrospective was not justified and consequently, Contractor was not liable to pay any LD. The Tribunal has held that completion of works as a whole i.e., last Key Date could not be achieved by the Contractor for the reasons attributable to Bangalore Metro. Since, most of the claims were linked to the aspect of delay, based upon the findings given on delay, the claims of the parties were decided. The Tribunal made it clear that claim towards idling & overstay could not be considered, due to existence of prohibitory clause in the Contract agreed upon by the parties, which specifically provided that Contractor shall not be entitled to claim any amount towards compensation,  damages or cost on account of delay attributable to Bangalore Metro and in view of the precedents of the Supreme court to the effect that Arbitral Tribunal which is a creation of the Contact cannot go beyond the terms of the contract.

The Tribunal allowed several claims of the Contractor with specific directions to issue Performance Certificate, release the BGs, Final Bills, compensation for delay in release of payments towards Interim Bills, charges for extension of BGs from time to time, allowing the claims towards price variation of major construction materials, claim towards Quantity variation, amounts withheld towards execution of additional works, etc., and also holding that Contractor is not liable to pay any LD. Apart from claiming LD, Bangalore Metro had also claimed penalty for not achieving Key Dates, additional payment to GC & few other claims. Interestingly claim for loss of productivity was also made by Bangalore Metro on the ground that due to delay in completion of Project work, train operations were also delayed resulting in loss of revenue.   The claims were rejected by holding that the contention of the Contractor that having not levied any penalty while granting the first four extensions, Bangalore Metro was not entitled to recover any penalty subsequently, which were for Key Dates 1 to 4. Contractor had also contended that Contract did not provide for making any claims towards loss of productivity, risk & cost, etc., that too without any prior notice to the Contractor. We were also successful in convincing the Tribunal that though the contract provides that Time was essence of the Contract, such clause has no relevance, once extension is granted and  accordingly the Tribunal held that it was not the intention of the parties to treat time as essence of the Contract in view of the fact that Bangalore Metro had granted extensions on account of which it cannot hold Contractor alone responsible for delays.

In view of the awards passed, the Contractor has got the benefit of INR 52 Crores (USD 7.5 Million). On account of the directions given by the Tribunal to release the BGs the Contractor has got an additional benefit of INR 25.87 Crores (USD 3.7 Million). As already mentioned above, the Tribunal has also directed Bangalore Metro to issue the Performance Certificates and declared that Contractor is not liable to pay any penalty/ LD. This is a significant victory of the Contractor against a Public Authority like Bangalore Metro which had withheld the legitimate dues of the Contractor inspite of successful completion of infrastructure Projects on account of which the Contractor had suffered financially.

Search

Other Articles / Blogs by the Author

Practice Areas

Archives


Authors


slot thailandslot thailand gacorjudi online atau investasi legal mana yang lebih aman 1main game dapat point dana cuma 10 menit sehari begini caranya 1pola main game penghasil gopay coin yang bikin lebih aman 1ramai dibahas judi online tapi risikonya tak main main 1main game dapat point ovo hasil uji coba yang aman 1main game biasa atau game penghasil saldo dana mana cuan 1uji klaim game mahjong ways dapat saldo dana aman 1cek dulu sebelum coba game mahjong ways dapat saldo dana 2lagi tren main game gates of olympus hadiah point gopay cek 1permainan sweet bonanza dapat ovo cash atau jebakan 1promo resmi atau saldo gratis mahjong ways beri saldo dana 1mahjong ways beri saldo dana cek fakta dan risiko 2026 2game gates of olympus kejutan point ovo aman dicoba 1cek aturan promo saat main sweet bonanza kejutan ovo point 1