ICC Tribunal in Singapore decides limitation issue under Indian law

ICC Tribunal in Singapore decides limitation issue under Indian law

ICC Tribunal in Singapore decides limitation issue under Indian law

On 25 October 2017, International Chamber of Commerce’s (ICC) sole arbitrator, Cameron Hassall, agreed to hear the claims of China’s Sinosteel Equipment & Engineering (Sinosteel) against an Indian iron ore processor and exporter, MSPL. Claimant Sinosteel is China’s second-largest importer of iron ore in the business of management, supervision, design and manufacture of mechanical and electrical products in sectors including metallurgy, mining and energy.

(As published in China Business Law Journal published by Vantage Asia available on this link.)

The sole arbitrator, before proceeding with the merits of the dispute, at the outset decided to deal with the limitation issue related to the claims and counterclaims of the parties, and a partial award was delivered with regard to the same.

The arbitration was conducted in accordance with the ICC Rules, 2012 in Singapore as required under contracts signed between the parties, with the law of India being the governing law of the contracts. The law of Singapore was the law governing the arbitration agreements within the contracts, as well as the procedural law governing arbitration proceedings.

The companies had entered into three contracts relating to design, engineering, supply and technical services with respect to a pellet plant in the state of Karnataka with a capacity of 1.2 million tonnes per annum.

According to the contract, the equipment testing was to be done in three stages. The first two tests were conducted successfully, but the companies could not successfully conduct the third test.

The dispute arose after MSPL failed to fulfil its obligation and pay the claimant its dues for the completed part of the work under the contracts between them. The parties proceeded to make claims and counterclaims to prove how the claims of the other party were barred by limitation. All three contracts consisted of an arbitration clause and the dispute was accordingly referred to the arbitration.

The claims of the claimant concerned payments in stages under the three contracts, which the respondent had failed to make. The respondent’s counterclaims, on the other hand, hinged on reimbursement for the expenditure incurred to rectify the damage to the pellet plant due to the claimant’s non-performance of contract, and liquidated damage for the breach of the contracts.

Indian law of limitation and the effect of acknowledgment. In India, as per the Indian Limitation Act, 1963, the parties have the right to sue for dues unpaid, until the period of three years from the date on which the right to sue arose. A suit filed after the period of three years is barred by limitation and there lies no valid claim after that. Section 18 of the Indian Limitation Act 1963, stipulates that the period of limitation will be extended in the event of an acknowledgment of liability made by the debtor before the expiration of the period of limitation to initiate the recovery process.

Acknowledgment means a definite admission of liability; it is not necessary that there should be a promise to pay, and the simple admission of a debt is sufficient. Acknowledgement is a statement in writing that a debt is due and unpaid.

The main legal point of contention between the parties was regarding the relevance of “conditional acknowledgment of liability” in determining time limitation. The acknowledgment/conditional acknowledgment of liability by a party against whom a claim is made will extend the limitation period. According to section 18 of the Indian Limitation Act 1963, a fresh limitation period will be computed from the date of such acknowledgment of liability.

Objections raised by the parties regarding the time limitation issue. The respondent had raised time limitation objections on the claims of the claimant, citing that the cause of action would accrue once the credit period mentioned on the invoices raised by the claimant expired. The claimant was resisting this objection on the basis of the respondent’s acknowledgment of debts in terms of section 18 of the act. Once the respondent acknowledges its debt, a fresh period of limitation begins from that date.

The entire contention of the respondent, on the other hand, was that there was no acknowledgment at all, rather the acknowledgment was contingent on the condition that the payment must be made only when the claimants successfully conduct the guarantee test contemplated under the contract. The respondent had argued that the fulfilment of the condition was mandatory so that acknowledgment under section 18 could be formulated, and such condition had in fact never been fulfilled.

Another interesting objection raised by the respondent to the claimant’s reliance on acknowledgments was that such acknowledgments had been made via emails, whereas Indian limitation provided that acknowledgments should be in writing. However, the claimant relied on the Indian Information Technology Act, as well as various case laws, to establish that acknowledgment via emails amounts to acknowledgment in writing.

The claimant also raised limitation objections to the claims of the respondent on both counts, i.e., the liquidated damages as well as the expense claims.

THE FINDINGS
Ld. sole arbitrator, with the help of various precedents and as cited by the parties, explained that even if an acknowledgment is accompanied by a refusal to pay, it is sufficient acknowledgment for the purposes of section 18 of the Indian Limitation Act 1963. To see whether an acknowledgment is valid or not has to be construed liberally, but fairly. In view of the same, the Ld. sole arbitrator held that all the ingredients of acknowledgment under section 18 were satisfied by the conditional acknowledgment made by the respondent and its denial to pay does not affect the acknowledgment for the purposes of section 18 of the Indian Limitation Act 1963. In view of the same, the claims of the claimant were held to be within limitation.

The respondent’s claims relating to liquidated damages, on the other hand, were rejected as being barred by time limitation. The expense claim of the respondent was left open to be contested on limitation at a later date.

Limitation bars the remedy; it does not extinguish the right. Therefore, provisions under section 18 of the Indian Limitation Act 1963, aid in restoring such rights. The claims of Sinosteel were saved by section 18 of the Indian Limitation Act 1963. This provision refreshes the prescribed three-year limitation period when an acknowledgment of liability is made by the opposite party before the expiration of the period prescribed.

Singhania & Partners was counsel to Sino Steel. The team included partners Ravi Singhania and Shambhu Sharan, senior associate Gunjan Chhabra, and associate Shashaank Bhansali.

Ravi Singhania is the managing partner and Gunjan Chhabra is a senior associate at Singhania & Partners in New Delhi

Search

Practice Areas

Archives


Other News

We are an extension of your in-house legal team

The client’s satisfaction is evident from years of their association with us, more than a decade for a lot of them. We act as an extension of in-house legal teams and act as External Legal Counsel to you. Our efforts are towards being strategic partners in your growth and not to be just a law firm.

Contact us